Seloitte hires PopTal for developing a new mobile application. PopTal team follows Agile methodology for development and estimates the whole project to take up to 1000 points. In the first sprint the team commits to work on the following stories:

Story 1 - 6 points
Story 2 - 10 points
Story 3 - 16 points
The team completes Story 1 and 3 but only completes eighty percent of Story 2. Pick the correct statements:

A: The average velocity of the first sprint is 22 points
B: The average velocity of the first sprint is 30 points
C: Based on the average velocity, the product owner can notify the stakeholders that the project will take roughly 45 sprints to finish (assuming team size and members remain the same)
D: Based on the average velocity, the product owner can notify the stakeholders that the project will take roughly 33 sprints to finish (assuming team size and members remain the same)