Here’s a sprint burndown chart for team A at SpaceY Inc:
Burndown Chart 1 image
Here’s a sprint burndown chart for team B at SpaceY Inc:
Burndown Chart 1 image
We know the following about the graphs:

- Red line is the the ideal line: projected slope that depicts how the team progress would look like
- Black line is the actual effort line
- Story points are represented on Y-axis
- And time in weeks is represented on X-axis

Which of the following statements are true about SpaceY teams:
P: Team A started slowly and was moving behind schedule. Yet, they managed to finish the sprint in time
Q: Team A is working hard towards meeting the deadline but isn’t updating the burndown chart throughout the process, only at the end.
R: Team A’s next sprint’s capacity should be burned down or decreased so that the team can have to complete tasks/story points from the previous sprint
S: Team B started slowly but eventually caught up
T: Team B might have overestimated the project’s timeline